Driveway drainage upgrade (May 28 update)
May 28 update: We are excited to announce that the driveway drainage project is expected to be fully complete by Wednesday, Jun 5. Note: the Ontario St. & 51st Ave access will be closed on Friday, May 31 and Saturday, Jun 1. Please use the 49th Ave entrance during these days. Thank you for your patience as we conduct these necessary upgrades.
May 23 update: On Friday, May 24, contractors will be grinding off asphalt and grading. Please note: the Ontario St. & 51st Ave access to the parkade will be closed at times throughout the day. We encourage you to use the 49th Ave entrance to access the parkade. Paving work will occur on Saturday.
May 21 update: We are on schedule for the final week of construction. Continue expecting delays at the Ontario St. & 51st Ave entrance. Please proceed with caution around construction zones.
May 15 update: The Ontario & 51st entrance will be closed tomorrow. Please use the 49th Ave & Columbia access to enter / exit the parkade.
For parking: Parking spots flanking the driveway by the Ontario St. entrance will be unavailable. All other parking, including the north parking lot and the Handy Dart Drop off remains available.
May 10 update: The final phase of the driveway drainage upgrade will take place between May 11-29. Please note the following:
- Sat, May 11: 49th Ave & Columbia St access will be closed.
Please use Ontario St. & 51st Ave to enter/exit the parkade. - May 13–29: Expect delays at the Ontario St. & 51st Ave entrance. Please enter/exit the parkade from 49th Ave. & Columbia access to minimize disruption.
- May 13-17: evening work from 5:00 pm–9:00 pm. Expect delays at Ontario St. & 51st Ave. in the evening.
- May 21-25: daytime work. Expect delays at Ontario St. & 51st Ave. all day.
- May 26: line painting in the evening
- May 27-29: clean-up
Please note: these is an estimated schedule provided by our contractors. Times may change due to the nature of their work. Thank you for your patience as we improve the safety and quality of our roads.
May 7 update: Phase 2 of the driveway drainage upgrade will commence on Saturday, May 11. Please expect periodic closures at the Ontario St. access between May 11-21 29 as we complete the necessary work to conclude this project. We highly encourage all employees who drive to reroute and use the West 49th Avenue access (entrance by T Building) during this time. We look forward to providing you with the next update.
Please note:
- On Saturday, May 11, the 49th St. access (by T building) will be closed for the day as we complete paving the southwest corner.
- For Ontario St. access closures, we will post a sign at the corner of 49th and Ontario to indicate whether the entrance is OPEN or CLOSED.
May 3 update : Phase 1 remains on schedule to be completed for May 6th – the first day of classes.
An update on the daily activities over the weekend is as follows:
- Friday: Currently finishing Grading.
- Saturday: Saw cutting, remaining grading work and demobilization of some heavy equipment.
- Sunday: Asphalt Paving (10.00 a.m. to 7.00 p.m.) and Line Painting (Evening / Night Works)
The parkade will remain open with a traffic control during all weekend works; expect delays in and out of the parkade on Sunday.
We would like to thank the Langara Community for their cooperation and patience over the past couple weeks as we renew the drainage infrastructure and roadworks.
Reminder: Access to campus off of 49th Avenue will be for contractors only. Access to the parkade will be available at all times during construction during regular operating hours, however, minimizing the need for the parkade is encouraged. If you don’t need to bring your car to campus during intersession, walking, biking and transit is encouraged. The employee preferred lot and parking in the south east corner lot will be available to all on campus.
May 2 Update: Phase 1 remains on schedule to be completed for May 6th – the first day of classes.
- Paving starts tomorrow, Friday May 3rd and will continue into Saturday May 4th.
- Expect longer delays while entering and exiting the parade throughout these two days.
- Minimizing the need for the parkade is encouraged. If you don’t need to bring your car to campus, walking, biking and transit is encouraged.
- The employee preferred lot and parking in the south east corner lot will be available to all on campus.
Apr 30 update: Phase 1 is on schedule to be completed for May 6th – the first day of classes; this includes the majority of the disruptive work during operating hours.
- Wednesday – pouring concrete curbs
- Thursday – curing of curbs and road prep
- Friday & Saturday – paving
- Sunday – Line painting
Please note:
- Employees: Please use the Ontario St. access during intersession. The 49th Avenue entrance will be for contractors only during the intersession period.
- Single lane access to the parkade will be available at all times through construction during regular operating hours; however, minimizing the need for parking is encouraged.
- The Employee Preferred Lot and parking in the southeast corner will be available to all on campus.
- Daycare Drop Off has been relocated to the area east of B Building (look for the Temporary Daycare Drop Off Zone sign by the Recycling Depot).
- If you don’t need to bring your car to campus during intersession, walking, biking, and transit is encouraged.
Apr 16 update: The driveway drainage upgrade on the campus parking lot will begin as scheduled and continue throughout the intersession period, up to and including May 5. Please note: the 49th Ave entrance will be for contractors only during the intersession period. Employees: please use the Ontario St. access during intersession.
Mar 27 update: Starting during April intersession, the south driveway drainage on our parking lot will be repaired and then repaved. The scope of work is outlined in orange below. Access to campus off of 49th Avenue will be for contractors only throughout the intersession period. Access to the parkade will be available at all times during construction during regular operating hours, however, minimizing the need for the parkade is encouraged. If you don’t need to bring your car to campus during intersession, walking, biking and transit is encouraged. The employee preferred lot and parking in the south east corner lot will be available to all on campus.
If you have any questions or concerns, please do not hesitate to contact Facilities at facilities@langara.ca.
Thank you.
Facilities Department